Toolbox

By Shabna Ullah

Work on the Berbice River Bridge is progressing with the high span completed and the slopes almost in position to allow for a free flow of maritime traffic before work continues on the retractor span.

Sloping spans have been added to both sides of the high span to allow vessels to pass freely

Sloping spans have been added to both sides of the high span to allow vessels to pass freely

An official with the bridge project told Stabroek News that “the high span has to start functioning first for us to continue working on the navigation channel [where the retractor span would be located].”

The installation of the five slopes on the eastern side of the high span is almost completed. This would be joined by two more spans to connect to the abutment at Crab Island. On the western side, four out of the five sloping spans have already been installed.

The official said too that they have already started to install the cluster piles with lights for the free movement of vessels at night. An advertisement informing maritime traffic about piles was also shown on television in Berbice.

Cluster piles were installed to guide ships

Cluster piles were installed to guide ships

During the second media tour of the bridge on May 15, Bert Carter, chairman of the technical team had told reporters that the last section of the bridge to be constructed is the retractor span. The bridge which would be less than two miles long would be fitted with a total of 39.

Carter had said that upon completion of the high span, maritime traffic, especially from the bauxite company, Oldendorf would be able to pass under the high span unimpeded as installation of the other spans continues.

The height under the retractor span is 40 feet while the distance between the two pontoons that support the high span is 120 feet.

A tug belonging to the bridge project preparing to go under the high span

A tug belonging to the bridge project preparing to go under the high span

Carter had told reporters that when completed, the bridge will be the sixth longest floating bridge in the world at 1,570.719 metres. The Demerara Harbour Bridge is the fourth longest of its kind in the world. The Berbice Bridge will be shorter than the Demerara Harbour Bridge but the width will be the same, about 22 feet.

Seventeen spans have been positioned on the western side while the first and second spans have been left out to avoid persons going onto the bridge.

The original design of the bridge, which is said to have a lifespan of over 30 years and costs almost US$40M, was for the high span to be positioned on the western end of the bridge.

But the design was adjusted for the high span to be placed at the eastern end. The change was made to facilitate a better flow of the river traffic.

Reef sand at Palmyra

Reef sand at Palmyra

The abutment piles which are already in place would “have to be tied back on the land. The second tie back is in place to close off the western abutment.”

This newspaper was told also that sanitary blocks are being constructed on the eastern and western side “for staff and for the public.”

According to the official, two generator stations have been built on both sides and the generators now have to be installed. He said too that the construction of a security building is in progress.

Toll

Upon completion the administrative building and the toll plaza would be established at D’Edward. While tolls would only be collected on the western side of the bridge, a mini toll station would also be erected on the eastern side.

Vehicles would be allowed to cross with up to 40 tonnes and trucks would have to be weighed and may have to pay another toll, depending on the weight.

The average toll for a vehicle will be around $1,400 [costs would vary for different classes of vehicles] but no charge will be levied for individual passengers. This amount was calculated on the basis of a formula intended to secure sufficient revenue to cover all operating and maintenance costs, return on investment and repayment on financing.

Chairman of the Berbice Bridge Company Inc, Geeta Singh-Knight had said that the contractors – Bosch Rexroth and Mabey & Johnson – would be handing over a fully lit bridge, including on the high span [and under the high span for the ships] and retractor span as well as lighting on both ends of the access roads.

Deadline

The deadline for the completion of the bridge has been set for September and the official is hopeful that this would be met. The official also believes that the road would be “drivable” by next month, if not completed.

“You do not have to get a completed road for it to be passable. Work could still go on even after the bridge is opened to the public,” he said.

The contract for the road project was signed for US$8.7M and was undertaken by Dipcon Contracting Company.

This newspaper visited the access road at Crab Island and was transported along it to the Palmyra end. The laying of reef sand – of which 30% is mixed with white sand – was in progress at both ends.

However officials told this newspaper that they are facing a setback with the inclement weather as well as with sourcing the reef sand from the backlands [due to poor dams] for the Crab Island side.

In efforts to meet the deadline, they attempted to upgrade the access dam at Cotton Tree. Unfortunately the night before they had planned to traverse the dam the rain “washed out” their efforts. They are in the process now of sourcing the sand from another area.

Leslie Wason, a consultant/Inspector of Works with the ND Lea consulting firm, told Stabroek News  that the most technical part has been completed, referring to the linking of the two roads.

He too is confident that the access road can be completed on schedule but said the workers have to redouble their efforts and work late at nights. He said that after applying the reef sand, workers would top it with crusher run before laying the asphalt. According to him, “once the weather permits the work can be done in one month.”

He pointed out that the access road at D’Edward is currently receiving the final layer of reef sand.
A superintendent with Dipcon, Kumar Bickram said that two culverts are being constructed – a C22 that links Crab Island to Palmyra as well as a C9 – and they are both 50% completed.

Rawleston Adams, senior engineer with the Ministry of Public Works had told the media during the tour that the road is expected to be completed in two phases. The asphalt project should be finished by the first week in September in time for the commencement of the bridge operations.

The completion of the contract, he said, is set for April 2009, “giving the contractor another six months in terms of tidying up to install street lights and mark the road…”

Related Articles


You can follow responses to this article through its RSS feed.

Subscribe to our electronic edition or get home delivery!


Reader Comments

You can discuss this and other articles in our new community forums!


  1. Satish UNITED KINGDOM says:

    Excellent News:
    I was not aware that shipping traffic, would be able to pass unimpeded under the high span of this bridge. This is a truly excellent project which will mean people would not have to wait in humiliation for the ferry any longer.

    This daring project is a fitting signature for the current administration. Well done the brave souls who conceived and orchestrated this freedom for Berbicians!

    Today’s dreams are often Tomorrow’s reality!

  2. coolieman UNITED STATES says:

    Thank you stabroek news you did a fine job with this one keep it up

  3. A380100 UNITED STATES says:

    Great news. I am certain that business will now reach far into that county.

  4. dreaddy2 BARBADOS says:

    If it’s such great news why don’t you guys come back home. I still think we have not learned from the lessons taught by the Demarara Harbor bridge. The parable of the man who built his house on sand seems applicable here. From what I heard on the streets in Berbice, a permanent bridge by the narrows in the vicinity of the Berbmine plant made a whole lot more sense.

  5. rwilliams CANADA says:

    Good job !
    Now, lets move forward with the Freedom of Information Bill, Broadcasting Legislation – facilitating private broadcasters, proffesionalise the Police Force and make it accountable to parliament, build the capacity of and strengthen the judiciary, support and finance micro and medium businesses, particularly agro business, to help lift the poor out of poverty, economic insecurity and desperation.
    The above are inseparable in providing the progress,stability and security the society needs.

  6. jmohabir UNITED STATES says:

    Not waiting 8 Hours to cross…. WOW

    Keep it up my .

  7. Ricardo UNITED STATES says:

    Great Going!!!! Although we need the bridge to be completed soon, guys take your time and do an excellent job.
    the waiting days to cross with the ferry or barge will soon be o’er. Can sleep a bit later to get to Suriname now. No more 3:00 departure from home hoping to catch the 6:00 ferry

  8. Ron ANTIGUA AND BARBUDA says:

    Big Up to our great president Bharrat Jagdeo…. God bless you. You did so many good things for our country and this is coming straight from the Virgin Islands. Keep up the good work that you have accomplish. Hope others will observe and learn.



Leave a Reply

About Comments



The Comments section of this website is intended to provide a forum for reasoned and reasonable debate on the newspaper's content and is an extension of the newspaper and what it has become well known for over its history: accuracy, balance and fairness.

We reserve the right to edit/delete comments which contain attacks on other users, slander, coarse language and profanity, and gratuitous and incendiary references to race and ethnicity.

Curious about the little images next to each commenter's name ? Go here and sign up using the same email address you used to register for Stabroeknews.com then upload your image and confirm it.

More articles in Local News