Construction work on the new government complex which is to house several agencies including the Ministry of Labour, Human Services and Social Security has been moving at snail’s pace and despite several deadline extensions the work is far from half-complete nearly a year after it started.

The building is being constructed at a cost of $600M on a plot of land at Princes and High streets, where the Guyana Broadcasting Corporation (GBC) was once located.

Contacted last evening Labour Minister Manzoor Nadir told Stabroek News that the contractor Kishan Bacchus is to be blamed for the sloth in the project. He said that when he visited the site about three weeks ago, the work was only 40% complete and the new deadline date for completion is April 30.

Efforts by this newspaper to contact Bacchus for a comment were unsuccessful.

The Minister explained that construction started in April last year and the deadline date for completion was the end of December. However it was owing to problems obtaining construction material and the weather that the consultant gave a five-month extension.

“The progress is painfully slow. If he continues at this rate and if we allow him to, we are looking at another 10-12 months”, Nadir told this newspaper adding that “The new deadline is the end of April. That is virtually impossible for him to meet unless he is superman”.

Asked how the delay is affecting the employees, he said that they are all very disappointed but they have to cope with the situation since work has to continue.

Nadir further said that “there are some processes that we have to go through”, what asked about the actions that will be taken against the contractor.

In 2001, a decision was taken by government to construct a new building after the ministry’s operation was decentralized following a fire. The Ministry is presently housed at Cornhill and Water streets with other locations at Brickdam, Camp Street and North Road.

The new building which is to be a two-storey one with about 65,000 square feet, is to house these four locations as well as several government agencies.

In July last year the Government Information Agency (GINA) had said that the foundation was laid and that work was being done to frame curb walls and erect columns.

Nadir had said on that occasion that they were looking to award the contracts for the electrical aspect and the design for the air conditioning of the building.

Related Articles


You can follow responses to this article through its RSS feed.

Subscribe to our electronic edition or get home delivery!


Reader Comments

  1. poor people fedup GUYANA says:

    600 million to build a two storey building and the elecrical trimmings are not included? what the hell……..?

    • Durbie UNITED STATES says:

      Poor People, There is a reason why you are poor. No analytical intelligence. A 65,000 sq ft building costing only $600MM is cheap. What kind of building is that? Are they making it with mud and coconut branch?

  2. CFO GUYANA says:

    Their approval of the extensions suggest that they accept the reasons for delay.

  3. guyanesetodbone TRINIDAD AND TOBAGO says:

    What the hell you all expected, i a=have worked along with Mr. Bacchus on some projects,I cant wait for this government to be voted out of office, when is another story,but in the mean while the ppl of guy. will continie to suffer.



Leave a Reply

About Comments



The Comments section of this website is intended to provide a forum for reasoned and reasonable debate on the newspaper's content and is an extension of the newspaper and what it has become well known for over its history: accuracy, balance and fairness.

We reserve the right to edit/delete comments which contain attacks on other users, slander, coarse language and profanity, and gratuitous and incendiary references to race and ethnicity.

Curious about the little images next to each commenter's name ? Go here and sign up using the same email address you used to register for Stabroeknews.com then upload your image and confirm it.

More articles in Local News