An extension from the April 30 deadline which was given to contractor Kishan Bacchus for the construction of a new government complex at the corner of High and Princes streets is currently being processed.

No major work was being done on the new government complex under construction at High and Princes streets when this newspaper visited yesterday.

No major work was being done on the new government complex under construction at High and Princes streets when this newspaper visited yesterday.

Stabroek News understands that a private consultant is currently working out an extension period to determine a new deadline for the completion of the building which is expected to house among other agencies, the Ministry of Labour, Human Services and Social Security.

When this newspaper visited the site yesterday minor masonry work was being carried out.

An official at the site said it was unclear when the project will be completed but added that it might take more than five months. He said almost half of the planned volume of work had been completed.

When contacted recently for a comment Minister of Labour, Manzoor Nadir, said he was unable to do so. Nadir had earlier told this newspaper that the contractor was to be blamed for the sloth and non-completion of the project at its initial deadline. Regarding actions which would have been taken against the contractor, the minister had said that there were processes which were to be undertaken.

Construction of the two-storey complex started in April last year and was expected to be completed last December.

However, problems obtaining materials and poor weather conditions at the time saw the project’s consultant giving a five-month extension.

Last July, a Government Information Agency (GINA) report stated that the building‘s foundation was laid and work was carried out to frame curb walls and erect columns. Nadir had said on that occasion that contractors were being sought to undertake electrical works as well as the design for the air conditioning of the building.

The 65,000 square feet building is being constructed at a cost of $600 million on a plot of land where the former Guyana Broadcasting Cor-poration once stood. The Labour Ministry’s operations were decentralized following a fire and the administration took the decision to construct a new building to house the ministry in 2001. That ministry is currently housed in buildings at Water and Cornhill streets, Camp Street, Brickdam and North Road.

Related Articles


You can follow responses to this article through its RSS feed.

Subscribe to our electronic edition or get home delivery!


Reader Comments

You can discuss this and other articles in our new community forums!


  1. Witch DR. CANADA says:

    Too many trees are being wasted on this construction site.Talk about going green!!!!

  2. Caesar Agustus UNITED STATES says:

    This is a joke. Looking at this job it will take six months to complete.There is still roof dry in,Electrical, Plumbing and Mechanical, Airconditioning, Low voltage security , Firesafing,doors and windows, interior and exterior finishing,fire alarms, life safety including disibility act accessibility,and final structural inspection for certificate of occupancy.Before this building can be occupied.

  3. Ankoko UNITED STATES says:

    Piss poor planning, inefficiency, patronage contract and all that jazz leads to this.
    Doubt if any publicity will be given to the cost overruns and shoddy work that will be obvious soon after the building’s occupation.

  4. iron-monkey CANADA says:

    google skyjack thats the way to go,,,,green is a word that will be abuse for another 20yrs



Leave a Reply

About Comments



The Comments section of this website is intended to provide a forum for reasoned and reasonable debate on the newspaper's content and is an extension of the newspaper and what it has become well known for over its history: accuracy, balance and fairness.

We reserve the right to edit/delete comments which contain attacks on other users, slander, coarse language and profanity, and gratuitous and incendiary references to race and ethnicity.

Curious about the little images next to each commenter's name ? Go here and sign up using the same email address you used to register for Stabroeknews.com then upload your image and confirm it.

More articles in Local News