Hope Canal completion date still June 2013 – Wordsworth

Despite being only 13.5% complete up to the end of October, the eight-door sluice for the Hope Canal as well as the entire Hope Canal Project is still expected to be completed by June 2013, Chief Executive Officer of the National Drainage and Irrigation Authority, Lionel Wordsworth says.

Last week, Minister of Agriculture, Dr Leslie Ramsammy had expressed concern over the slow pace of construction of the sluice and Wordsworth said that the contractor, Courtney Benn Contracting Services Limited is working extended hours with an increased workforce. The entire project has a June 2013 completion deadline.

The $3.6 billion canal, when completed, is expected to help drain the East Demerara Water Conservancy (EDWC) into the Atlantic Ocean. Currently, when the water reaches a high level in the EDWC, it is drained through the Maduni and Lama sluices into the Mahaica and Mahaicony creeks resulting in overtopping and flooding in these areas.

Excavators building up the embankment at the Hope Canal in September (Stabroek News file photo)

Asked about the slow pace of the construction of the sluice, Wordsworth told Stabroek News yesterday that the contractor had indicated that there were issues with the availability and timely supply of greenheart timber piles to meet the requisite specifications, transportation difficulties of the piles during the Linden protest and the mechanical failure of the diesel hammer during the driving of piles which resulted in a new hammer having to be procured.

In order to get back on track, the contractor has now placed additional pile driving equipment (drop hammer) on site which is operable, Wordsworth said. He said that driving of the greenheart  foundations piles with the drop hammer and the newly commission diesel hammer is being done with a substantial amount being completed.

In addition, Wordsworth said, the contractor is working extended hours with an increased work force. He added that 90% of the remaining piles are stockpiled on site and 100% of the steel sheet piles are on site already prepared and driving is currently ongoing. Simultaneously, the contractor is now driving steel sheet piles, greenheart piles and sandfilling and these are ongoing, the NDIA boss said.

Wordsworth said that the work completed was 13.5% up to the end of October with a notable increase in progress over the past eight weeks.  “The June 2013 completion date is expected to be met,” he emphasized adding that the entire Hope Canal Project is still expected to be completed by June 2013.

“The canal is now 83% completed and the installation of geotextiles reinforcement has commenced along with trimming and shaping of the channel embankment are in progress,” Wordsworth said.

Back in September, Ramsammy had said that Courtney Benn needed to finish the driving of the piles by the end of November. “If they finish by the end of November they will be able to finish the work [in time for June] because that is the major part of the work,” he had said.

More in Local News

Jaikarran Chandradeo

Two more held as cops look for motive in Corentyne triple murder

Police yesterday detained two more persons as they continued to try to unravel the motive behind the gruesome shooting to death of two men and a teenage boy, whose bodies were discovered at Kokerite Savannah, Mibicuri Creek, on Friday.

These children enjoyed being pushed home by a cousin

Riverstown

Riverstown, a village on the Essequibo Coast, is pressed between Pomona and Airy Hall. Once you cross the railway-like bridge over a black water creek, you’re in Riverstown, where there are more than 700 residents.

Raphael Trotman

SARU operating legally despite absence of legislation

Minister of Natural Resources, Raphael Trotman said on Thursday that the State Assets Recovery Unit (SARU) is operating legally and despite its inability to prosecute persons, it is currently doing investigative work which is part of its mandate.

Dead: Orin Morris

Sophia stevedore killed in freak accident at wharf

The body of a stevedore attached to the John Fernandes Limited, Water Street wharf was retrieved from the Demerara River on Thursday evening, more than a day after he was involved in a freak accident.

The old abandoned Moco-Moco Hydropower Station

2018 deadline set for completion of Moco-Moco hydropower facility

Due diligence is currently being done on two firms that had bid to rehabilitate the Moco-Moco hydropower facility and the project should be completed by the end of 2018, Minister of Public Infrastructure David Patterson says.

Devika Tinsarran after she lost all her hair due to chemotherapy treatment for breast cancer.

Breast cancer survivor turned advocate urges women to get screened early

For many who receive a breast cancer diagnosis, hearing from others who have survived it can be a great source of comfort and support.

Comments

About these comments

The comments section is intended to provide a forum for reasoned and reasonable debate on the newspaper's content and is an extension of the newspaper and what it has become well known for over its history: accuracy, balance and fairness. We reserve the right to edit or delete comments which contain attacks on other users, slander, coarse language and profanity, and gratuitous and incendiary references to race and ethnicity.



Stay updated! Follow Stabroek News on Facebook or Twitter.

Get the day's headlines from SN in your inbox every morning: