Amaila access road far behind schedule

Construction of the Amaila Falls access road is so far behind schedule that the contractor Fip Motilall is not likely to substantially complete the road before December.

Motilall’s company, Synergy’s Holdings, according to Senior Government Engineer Walter Willis, has so far completed approximately less than 35 per cent of the entire project. The deadline for the completion of the US$15.4M project was originally September 9.

Willis explained that the company is likely to claim