Olympic-size pool cost over half a billion

Design and engineering problems delayed the construction of the National Aquatic Centre, which houses Guyana’s Olympic-size swimming pool, and drove the total cost up to $581M, the Ministry of Sport disclosed yesterday.

In a written response to a question by AFC MP Khemraj Ramjattan about the Liliendaal facility’s cost, Minister Dr Frank Anthony detailed the figures for consultancies for design and supervision, and construction, which totalled $581,367,932. In a press release yesterday the ministry also outlined design and engineering difficulties that plagued the project, necessitating reviews and resulting in a six-month suspension of works at one point.

Frank Anthony

The centre was opened in November last year, although government has committed to adding a 25-metre warm up pool on site, to cater for international competitions and training for local swimmers.

According to Anthony, consultancies for design and supervision, provided by E&A Consultants Inc, Fotcon and Vikab, cost $22,534,500. Construction, meanwhile, was pegged at $558,833,432, with services provided by Kares Engineering Inc ($276,195,151); Myrtha Pools USA ($208,396,407); Guyana Power and Light ($4,249,268); Guyana Water Inc ($3,400,000); R Persid Construction ($20,246,127); Pioneer Construction ($9,796,270); Dipcon Eng-ineering Services ($23,013,350); G Bovell Construction ($3,488,870); as well as liabilities covered  by the ministry ($10,037,989).

In a statement accompanying the cost breakdowns, the ministry revealed that Fotcon and Vikab did the original design for the centre, and Kares Engineering was subsequently awarded a $316,394,320 contract for construction, from eight companies that bid for the project. The engineer’s estimate had been $425,127,099. In addition, E&A Consultants Inc was selected from three companies for a $13,363,500 contract to provide supervision services.

Work began in February of 2008, but by March “a number of design issues developed,” the ministry said, adding that a review was done by the technical team and adjustments were made. Nonetheless, the difficulties “persisted” and the ministry said works were suspended between November 19th, 2008 and May 18th, 2009. When works resumed, engineering problems, however, resurfaced.

According to the ministry, in August 2009, after consultations with Fédération Internationale de Natation (FINA)—the international governing body of swimming—Myrtha Pools was invited to do a presentation and it subsequently submitted a pre-engineered pool for consideration to project engineer Walter Willis.

It added that an extensive review was done by a team headed by Willis and it recommended that the scope of works for Kares be reduced, while Myrtha Pools be contracted to design and build a pre-engineered pool (50m x 25m x 2m).

Cabinet, in November the same year, approved the proposal and the company was contracted for $241,246,407 while the scope of works for Kares was reduced to $214,455,290. Myrtha, contracted on December 1, 2009, completed its contract in August 2010, the same month that Kares completed its work. However, additional works were required. “Despite the pool being functional, there was need for additional work on the pool site,” the ministry said, citing the need for installation of concrete drains, seating tiers on the grass mound, paved parking, security lights and a guard hut. It added that four companies—R Persid Con-struction, Pioneer Construc-tion, Dipcon Engineering Services, G Bovell Construction—were hired after public tendering and the additional works were completed in June of last year.

Yesterday’s answer in Parliament and the press release were the most detailed information yet from the ministry on this project. The pool has also been the subject of controversy over arrangements for its use.