Two sections of Amaila access road almost completed

A section of the Amaila Falls Access road recently

Two sections of the Amaila Falls Hydropower Project’s Access Road are nearing completion and the contractor is working to complete the 40 kilometre segment of the roadway before Christmas.

The government cleared the allotment of four multi-million dollar contracts to local companies to complete the roadway after it terminated the contract awarded to Fip Motilall’s Synergy Holdings to build and clear the roadway.

A section of the Amaila Falls Access road recently

Government engineer Walter Willis, when contacted, could not comment on any aspects of government work and he noted that he would only do so when instructed by the administration.

However, according to a source, work on section three and four of the roadway, which stretch from the Butakari area to the Issano/Potaro Junction, are more than 70% complete. Work there is being undertaken by Toolsie Persaud Quarries.

The source related that the road work is being undertaken in phases; sand is first laid on the surface, loam is then plastered and compacted on the roadway and finally laterite is spread at the surface to cap the roadway. Less than 5 kilometres of work remain for the placement of loam on the road works being undertaken by Toolsie Persaud Quarries and within the next two weeks laterite will be used to cap the road, the source noted.

According to the source, the works began in May this year on that section of the road but the rains have hampered the movement of heavy duty vehicles operating in the area. He noted, however, that within the past month, the Hinterland area has experienced sunshine almost each day, resulting in works being done around the clock to the roadway.

He said that initially there were problems associated with the movement of machinery to various sections of the roadway but he noted that the contractors have coordinated and remedied the problem.

Previously, this newspaper had reported that the works may have been completed by October 31 but the timeline has been revised to December.

The contract for section three of the road is valued $373.2 million; section four, $246.003 million; section five, $182.35 million; and section six, $281.72 million.

Section two of the road is being done by the Ministry of Public Works while Ivor Allen is working on section five of the road, G Bovell Construction on section six and HN Pasha on section seven.

Recently, the US$506 million agreement for the construction of the Amaila Falls Hydro Project and Transmission Line was signed in Xian, China by Sithe Global and China Railway First Group (CRFG) and Finance Minister Dr Ashni Singh. The signing signals an important milestone in the development of the US$840 million Amaila Falls Hydro project, which is expected to start by mid-2013.

On Monday President Donald Ramotar met Inter-American Development Bank (IDB) President Luis Alberto Moreno at the office of the Guyana Mission to the United Nations in New York to discuss several key developmental plans including the Amaila Falls Hydropower project.

According to the Government Information Agency (GINA), Ramotar explained that the discussions were fruitful.

“We had a very good discussion, we spoke about Amaila and the stage where it’s at… you know the President of the IDB himself went to China and he has been very helpful in pushing this project. We all understand that this is a very big project and very important project for Guyana, for the bank, for Sithe Global, for all involved. It’s a very important project so, obviously we all are looking at it and bringing the first stage, I don’t think we are very far away from bringing a conclusion to the first stage, and then we will begin the second stage of construction,” President Ramotar said.

Moreno was also quoted as saying that there is still a lot of work to be done but that they were looking at all possibilities for the project.

Comments  

Charlestown shop owner shot during altercation

The police say they are investigating a shooting incident which occurred about 11:20 am today at Leopold and Breda streets, Charlestown during which shop owner, Jacqueline Lagnah, 55, of 83 Leopold and Breda streets, sustained two suspected gunshot injuries to her lower back.

Wave of looting shutters stores, spreads fear in Venezuela

CARACAS/SAN CRISTOBAL, Venezuela,  (Reuters) – A wave of looting by hungry mobs across Venezuela has left streets of shuttered shops in provincial towns and pushed some store owners to arm themselves with guns and machetes, stirring fear that the turmoil could spread to the capital Caracas.

NY man gets 41 years for killing Guyanese girl

Taariq Stephens (New York Daily News photo) A Brooklyn man got a 41-year maximum prison sentence yesterday for killing a 16-year-old Guyanese girl who authorities said rejected his advances.

Debutant Ngidi leads South Africa to series victory v India

PRETORIA,  (Reuters) – Debutant Lungi Ngidi took six wickets as South Africa defeated India by 135 runs to claim victory in the second test in Pretoria today and also win the series with an unassailable 2-0 lead in the three-match contest.

T&T judge grants injunction stopping highway project

(Trinidad Guardian) Environmental activist group Fishermen and Friends of the Sea (FFOS) has obtained an interim injunction barring the Government from continuing work on the first phase of the $400M Churchill Roosevelt Highway Extension to Manzanilla.

Your browser is out-of-date!

Update your browser to view this website correctly.

We built stabroeknews.com using new technology. This makes our website faster, more feature rich and easier to use for 95% of our readers.
Unfortunately, your browser does not support some of these technologies. Click the button below and choose a modern browser to receive our intended user experience.

Update my browser now

×