Hope Canal completion date still June 2013 – Wordsworth

Excavators building up the embankment at the Hope Canal in September (Stabroek News file photo)

Despite being only 13.5% complete up to the end of October, the eight-door sluice for the Hope Canal as well as the entire Hope Canal Project is still expected to be completed by June 2013, Chief Executive Officer of the National Drainage and Irrigation Authority, Lionel Wordsworth says.

Last week, Minister of Agriculture, Dr Leslie Ramsammy had expressed concern over the slow pace of construction of the sluice and Wordsworth said that the contractor, Courtney Benn Contracting Services Limited is working extended hours with an increased workforce. The entire project has a June 2013 completion deadline.

The $3.6 billion canal, when completed, is expected to help drain the East Demerara Water Conservancy (EDWC) into the Atlantic Ocean. Currently, when the water reaches a high level in the EDWC, it is drained through the Maduni and Lama sluices into the Mahaica and Mahaicony creeks resulting in overtopping and flooding in these areas.

Excavators building up the embankment at the Hope Canal in September (Stabroek News file photo)

Asked about the slow pace of the construction of the sluice, Wordsworth told Stabroek News yesterday that the contractor had indicated that there were issues with the availability and timely supply of greenheart timber piles to meet the requisite specifications, transportation difficulties of the piles during the Linden protest and the mechanical failure of the diesel hammer during the driving of piles which resulted in a new hammer having to be procured.

In order to get back on track, the contractor has now placed additional pile driving equipment (drop hammer) on site which is operable, Wordsworth said. He said that driving of the greenheart  foundations piles with the drop hammer and the newly commission diesel hammer is being done with a substantial amount being completed.

In addition, Wordsworth said, the contractor is working extended hours with an increased work force. He added that 90% of the remaining piles are stockpiled on site and 100% of the steel sheet piles are on site already prepared and driving is currently ongoing. Simultaneously, the contractor is now driving steel sheet piles, greenheart piles and sandfilling and these are ongoing, the NDIA boss said.

Wordsworth said that the work completed was 13.5% up to the end of October with a notable increase in progress over the past eight weeks.  “The June 2013 completion date is expected to be met,” he emphasized adding that the entire Hope Canal Project is still expected to be completed by June 2013.

“The canal is now 83% completed and the installation of geotextiles reinforcement has commenced along with trimming and shaping of the channel embankment are in progress,” Wordsworth said.

Back in September, Ramsammy had said that Courtney Benn needed to finish the driving of the piles by the end of November. “If they finish by the end of November they will be able to finish the work [in time for June] because that is the major part of the work,” he had said.

Comments  

Red Force slump to innings defeat as Jaguars finish unbeaten

GEORGETOWN, Guyana,  CMC – Jason Mohammed completed his seventh first class hundred but there was little joy for Trinidad and Tobago Red Force as Guyana Jaguars needed a mere 45 deliveries to pull off an innings and 81-run win in their final round match here today.

Pope warns Latin America about corruption, mentions Odebrecht

LIMA, (Reuters) – Pope Francis wrapped up his trip to Chile and Peru today by warning that Latin America was in a deep crisis from corruption, with politics in most countries “more sick than well.” Speaking in improvised remarks to bishops, he mentioned the scandal involving construction company Odebrecht, which has admitted to paying billions in bribes, as an example of greed run amok across the continent of his birth.

Buttler hundred hands England ODI series victory

SYDNEY,  (Reuters) – England’s Jos Buttler struck a belligerent unbeaten 100 to set up a 16-run win over Australia in the third one-day international on Sunday, as the touring side took an unassailable 3-0 lead in the five-match series.

Law to debar errant contractors coming by year end – Corbin

The Public Procurement Commission (PPC) hopes that by the end of this year debarment legislation would be in place as it will soon begin meeting with stakeholders on a draft.

House passes witness protection bill

A bill to provide a legal framework for the protection of witnesses was passed without amendment by the National Assembly on Friday evening despite arguments by the parliamentary opposition that it failed to take into account modern challenges.

Your browser is out-of-date!

Update your browser to view this website correctly.

We built stabroeknews.com using new technology. This makes our website faster, more feature rich and easier to use for 95% of our readers.
Unfortunately, your browser does not support some of these technologies. Click the button below and choose a modern browser to receive our intended user experience.

Update my browser now

×