Cost of Amaila road contract quickly surpassing original US$15.4M

As the road to the Amaila Falls project continues to lag behind schedule, the original contract sum of US$15.4 million that went to Fip Motilall’s Synergy Holdings Inc is quickly being surpassed by the additional expenditure the government must outlay to complete the project, with one estimate going as high as US$40 million.

Meanwhile Motilall said recently that US$15.4M was sufficient for him to have completed the road.

Motilall is defending his company’s efforts on the road, saying that not much has