Four companies bid for new St Rose’s High building

Four companies yesterday tendered to construct a new building to house the St. Rose’s High School on Camp and Church streets.

The estimated cost of construction is pegged at $450M based on the engineer’s estimate. The bids were opened under the Ministry of Education at the National Procurement and Tender Administration Board (NPTAB).

The decrepit building

The companies and their bids are as follows:

Ministry of Education

Construction of St. Rose’s High School at Camp and Church streets, Georgetown.

Company Name Amount Tender
Builders Hardware & General Supplies$401.6M
Chung’s Global Enterprise$344.3M
Sattaur Mohammed and Sons Construction$370M
Courtney Benn Contracting Service Incorporated$352.7M
Engineer’s Estimate $450.666.440