Work ongoing on Phase Two of Amazonia Mall

An artist’s impression of phase two of the project when completed.

With the aim of providing more entertainment options to Guyanese and especially residents on the East Bank of Demerara (EBD), former Guyanese and West Indies  cricketer Ramnaresh Sarwan is moving ahead with the expansion of the Amazonia Mall.

Currently, construction of Phase Two of the multi-million dollar project at Block M, Providence, EBD, is ongoing and is expected to be completed by mid-2020. Phase one of the project was completed approximately three years ago and is now home to Massy stores, the New Thriving restaurant and Fitness 53 gym. Construction of Phase Two started in October 2018.

“Presently, we have completed the foundation and flooring for the building and we are working on the external drains on the south side of the building. By the end of January, we will start erecting steel and so on,” the former cricketer told Stabroek News.