Weather stalling Amaila Falls road – Motilall

Fip Motilall

Contractor for the Amaila Falls access road Fip Motilall said that the prevailing La Niña conditions have affected work on the project, which is less than 25 per cent complete.

Speaking to reporters yesterday after the launch of the Environmental Social and Impact Assessment (ESIA) for the Amaila Falls hydro-power project, Motilall said that if the weather was favourable the road would be passable by August.  “I’m working with an August [deadline] to get you four-wheel access. If the rain continues I’m not going to hit it. No way,” he said.

Motilall’s company Synergy Holdings Inc was awarded the US$15.4 million contract to build the access road to the proposed site for the Amaila Fall hydropower