Olympic-size swimming pool could have been built for 1/3 of cost

Geotechnical engineer and groundwater hydrologist Charles Ceres says that Guyana’s Olympic-size swimming pool could have been built for one third of the money spent.

Minister of Sport, Dr Frank Anthony on Thursday in a written response to a question by AFC MP Khemraj Ramjattan about the cost of the National Aquatic Centre at Liliendaal detailed the figures for consultancies for design and supervision, and construction, which totalled $581,367,932. In a press release the ministry also outlined design and engineering difficulties that plagued the project, necessitating reviews and resulting in a six-month suspension of works at one point. The National Aquatic Centre houses Guyana’s Olympic-size swimming pool.

Speaking with Stabroek News yesterday, Ceres said that responsibility for the project rests on the engineers and the contractor cannot be blamed. “It comes back to the engineering,” he said. In a letter to