Haags Bosch accepting double capacity of waste daily

A covered cell at the Haags Bosch Landfill site (Photo courtesy of BK International)

BK International says the Haags Bosch Landfill that it was contracted to build and operate is accepting double the capacity of waste per day it was designed to accommodate and has presented ongoing challenges from the commencement of the project.

According to a press release from Public Communications Consultants Limited, BK noted the comments made by Georgetown Mayor Hamilton Green regarding the operations at the landfill as reported in the Monday edition of the Kaieteur News.

BK International was contracted to build and operate the landfill in 2010 in accordance with a design provided by government under an