Giftland Mall to start supplying GPL grid today

 Manager of GPL’s System Control and Engineering Services Deryck Phil training Giftland Mall operators as the preparations move apace to boost power supply. (DPI photo)
Manager of GPL’s System Control and Engineering Services Deryck Phil training Giftland Mall operators as the preparations move apace to boost power supply. (DPI photo)

The Guyana Power and Light Incorporated (GPL) will begin receiving a maximum 5 megawatts (MW) of power from the Giftland Mall on Sunday, according to the utility company’s Deputy Chief Executive Officer of Strategic Operations Samaroo Ramtahal.

“We are working aggressively to bring on this five-megawatts of power to the GPL grid because of the generation capacity shortage that we have. From time to time we have reliability issues, so we are hoping that this five-megawatts would be on stream Sunday,” Ramtahal was quoted as saying on Friday in a Department of Public Information (DPI) report.

The 5MW of power will be added to GPL’s Demerara-Berbice Interconnected System.

Ramtahal, who said the initiative forms part of GPL’s efforts to provide more reliable energy to Guyanese, was also reported as saying that the company is training 12 operators of the Giftland Mall to ensure a smooth transition and operation of the system when up and running.

“Today we are in the final stage … We have a full team here to provide the training, dot the Is and cross the Ts so that when we go live, we have no issues or challenges,” the Deputy CEO said.

The report said Manager of GPL’s System Control and Engineering Services Deryck Phil conducted the training.  

Speaking on the importance of the training, he said Giftland was like an island which supported itself, but when connected it will be “a different kettle of fish.” “You have a network of over 140 megawatts of power and they are just five megawatts. So, coming on to the network there will be a number of issues. They will have to be able to synchronise … their system with ours. They have to look at load flows; they have to understand the dynamics of the power system,” he explained. “We are going to have some of our operators spend about two weeks with them to give them a feel on operating the power system,” he added.

GPL will be paying Giftland Mall $35 million per month for the supply of energy through a Power Purchase Agreement.